Two factors determine the design thickness of pervious pavements: the hydraulic properties, such as permeability and volume of voids, and the mechanical properties, such as strength and stiffness. ACI 522R-10 states that pervious concrete used in pavement systems must be designed to support the intended traffic load and contribute positively to the site- specific storm-water management strategy. The designer selects the appropriate material properties, the appropriate pavement thickness, and other characteristics needed to meet the hydrological requirements and anticipated traffic loads simultaneously. Separate analyses are required for both the hydraulic and the structural requirements, and the larger of the two values for pavement thickness will determine the final design thickness. Numerous applications have used a 5- to 6-in. (12- to 15-cm)-thick pervious concrete over an aggregate base generally of the same dimension. Field performance of these projects has shown that they are adequate to handle the traffic loads expected in parking lot type applications (passenger cars), where the heaviest loads are generally from garbage trucks. If heavier loads and higher traffic are expected, then a thicker pavement (8–12 in. [20 –30 cm]) is used. Another approach would be to try to use the structural design techniques outlined in the ACI 522R report, which could help optimize the pavement thickness.
Initial recommendations had been that pervious concrete should be used only in sandy soils with an infiltration rate greater than 0.5 in./h. However, a detailed hydrologic analysis for a specific example with soils with infiltration rate of 1, 0.5, 0.1, and 0.01 in./h has shown that the postconstruction runoff was lower in all four soils when compared to the preconstruction runoff. The draw-down time in all cases was acceptable, except for the soil with the lowest infiltration rate, and that, too, only when an aggregate base was used. The authors concluded that pervious concrete can be used in silty soils with a soil infiltration of only 0.1 in./h and that there is no need to limit its use arbitrarily only to sands. In soils with infiltration rates considerably less than 0.1 in./h, one way to reduce the draw-down time could be to use buried perforated pipes that can transfer the collected water elsewhere. If that is not feasible, the pervious concrete system could be placed without an aggregate base and the resulting excess runoff over the pervious concrete (but still lower than if an impervious system had been used) could be handled using additional detention devices.
Subscribe to:
Post Comments (Atom)
Explore Modern And Traditional Construction Methods
A self-build home is the dream of any builder, architect, or even just those with aspirations for their perfect home. They take a lot of blo...
-
Timber stud partitions were an alternative to brickwork and could act as both loadbearing and non . loadbearing walls. If they were supporti...
-
These were very popular in the last quarter of the twentieth century and comprised two layers of plasterboard factory-bonded to a cardboard ...
-
A simple hinge swap provides 2 inches of extra width in a doorway We recently finished a bathroom remodel that included a new curdles sh...
No comments:
Post a Comment