Remodeling carpenters routinely set large beams in cases such as the one shown here, where the beam replaces a bearing wall. Whether a beam is made from engineered lumber or regular old 2x12s, the challenge is weight. Here, a new beam was made from three 16-ft.-long 13⁄4-in. by 117⁄8-in. LVLs. It would have been difficult to raise the assembled beam, but the trick is to raise one piece at a time and then fasten the three together in place. Replacing a wall with a beam requires carrying the loads while the old wall is being removed and the new beam is being installed. I built a temporary wall about 1 ft. beyond the old wall before removing it. I was lucky in that the joists above overlapped by several feet and so the temporary wall could be held back that far, which provided more room to work. In most cases, a temporary wall has to be built much closer to the existing wall, or even in contact with it, to catch the joist overlap and to support the floor. This beam was engineered for its loads. (Lumberyards often provide this service for free.) Each end of the beam imposes a substantial load that requires a direct path through the framing to the foundation. Here, one end of the beam landed above the foundation wall, while the other was directly over a column in the basement. To complete the load path, all I had to do was place squash blocks (double or triple studs cut to the depth of the floor joists) between the bottom of the subfloor and the main beam below. In other cases, I might have had to add new columns and footings to carry the newly concentrated loads.
1. Install kings and plates. King studs tie the beam ends to the existing framing. Cut a new bottom plate long so that fasteners don’t split it, screwing it to the framing below where the king and jack studs will go. Cut the plate flush to the jack studs later.
2. Mark the beam location. To keep the beam straight, snap a chalkline on the joists between the edges of the king studs for a guide.
3. Use the beam depth to size the jacks. Measure the depth of the beam stock, and mark that on the king studs. Measure up to the mark from the bottom plate to determine the height of the jacks.
4. Install jack studs and stop blocks. Two jacks were required at each end, but only one was installed at first to ease setting the beam. Temporary blocks on the jacks guide the beam placement.
5. Measure the beam length. Pull a tape between the king studs to determine the beam length. Deduct 1⁄4 in. from that number so the beam members don’t bind while being installed.
6. Slip the plies into place. With the top leaning in, place both ends of the first ply at once onto the jack studs. A few sledgehammer taps along the bottom face stand the ply up.
7. Install the remaining plies like the first. Nails can be used to join the plies, but structural screws set with an impact driver are better at drawing them into full contact with one another. Follow the designer’s fastening schedule.
8. Fasten to the joists. Join each joist to the beam with a 3 ⁄2-in. #10 multi- purpose screw driven at an angle. In some circumstances, framing hardware is required to resist seismic or uplift loads.
9. A wide opening. With the second jack studs placed, the bottom plates trimmed, the squash blocks placed below, and the temporary wall removed, the new beam is ready for drywall.
Subscribe to:
Post Comments (Atom)
Explore Modern And Traditional Construction Methods
A self-build home is the dream of any builder, architect, or even just those with aspirations for their perfect home. They take a lot of blo...
-
Timber stud partitions were an alternative to brickwork and could act as both loadbearing and non . loadbearing walls. If they were supporti...
-
These were very popular in the last quarter of the twentieth century and comprised two layers of plasterboard factory-bonded to a cardboard ...
-
A simple hinge swap provides 2 inches of extra width in a doorway We recently finished a bathroom remodel that included a new curdles sh...









No comments:
Post a Comment